Constructorator
  • Home
    • About
  • Blog
  • Tips
  • Foreman
  • Concrete Finishers
  • Layout Crew
  • online training
  • Contact
  • Share
    • Constructorator Spotlight
    • Women In Construction
    • Why I love Construction Videos
    • Technology Link Page
  • Search

Using SCC (Self-Consolidating Concrete) for Production Part 11.

3/18/2015

Comments

 
Picture
                 
                      For me, I have found that a 26" spread is the sweet spot for SCC placement; the flow seems to be perfect, as well as not needing to foam-fill every gap in the formwork. In fact a hole up to 13/16" will spew out for a second where you have time to shove a small rock, rag or something similar to stop the leak. Typically you will foam large continuous gaps along the bottom of the forms where it seats on the footing, along the bulkheads if the reinforcing penetrates and laps out or unused tie holes. But as far as the smaller one's the paste will leak but if you're not pouring a pea-gravel SCC mix with a 30" spread, you don't have to spend a lot of time filling every quarter inch hole. 
However the mud will flow, I have had success pouring core walls with the SCC traveling as far as 73',  around and through connected double reinforced 10" wall's. Which were placed from the bottom up using a wall port, the mix was pea-gravel the spread was 26", total yardage was 145 CY; the truck spacing was 6 minute splits. We had the first three trucks on-site before we started placing; the important part of pouring from the bottom up is not waiting! You risk losing being able to use the port and the pour if the concrete sits and sets while waiting for concrete trucks to show up. 
So if the only access is from the bottom up and its only 50 total yards, then its better to have all the trucks back to back and start placing once the last truck is batched to ensure a continuous pour. If it's going to be a 100+ yards then having a secondary port to be used as back up placed at a higher level on the wall, in case you have any problems you can go to the secondary port. 
Comments

Using SCC (Self-Consolidating Concrete) for Production Part 1.

3/11/2015

Comments

 
Picture
Typically when you hear the words "SCC" (self consolidating concrete) you think cost, leaks and formwork pressure. To only be used in areas with too much congestion so there is no way around it,  slab to beam walls or simply as a last resort. I feel SCC is one of the greatest resources out there for concrete construction! Yes, cost and form pressures are concerns, but you have to look at the possible benefits; time savings, manpower and astethetics. All of which can save you time and money. 

Why I love SCC?

What do you think about pouring core walls with heavy congested steel at 3:00 PM on a Friday? Typically you're thinking, "WOW we're going to be here all night!"
  • What you should be thinking; if we use SCC it will only take me one/two hours (depending on size, yardage etc...) to pour out, so I will be home for dinner.  How awesome is that? Not having to miss a scheduled day or make up a day.
Let's say you have limited resources for a job, so breaking down an entire crew to pour walls kills production on another task. 
  • If you use SCC you can limit placement to 2-3 guys. Leaving the remaining crew to keep the job flow going by working on other tasks. 
Yes, there are challenges with using SCC, the formwork has to be tight, designed for full liquid head and of course the cost. However, if you do your homework, cost comparison and have a great concrete supplier that has really dialed in the mix, you will see the benefits of using SCC for production. In my next few blogs I will be going into further detail about pouring SCC for production. 


Comments

    Categories

    All
    2015 Year In Review
    Blueprints
    Build Your Name
    Carpenter
    Change
    Concrete
    Concrete Construction Schedule
    Concrete Placement
    Construction
    Construction Technology
    Crane
    Foreman
    Homeowners
    How To
    Job
    Leadership
    Material
    Mentoring
    Order List
    Planning
    Post Pour
    Post-Pour
    Pour Cards
    Pre Pour
    Pre-Pour
    Productivity
    Safety
    Self Consolidating Concrete (SCC)
    Sequence
    Time Cards
    Tools
    Tower Crane
    Workflow

    Archives

    September 2018
    August 2018
    July 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014

    RSS Feed

    WANT TO CONTRIBUTE: EMAIL HERE 
Picture

Copyright © 2018 Constructorator
​
ALL RIGHTS RESERVED
Photos used under Creative Commons from StockMonkeys.com, elPadawan, Napolean_70, Seattle Municipal Archives, sndrv, FutUndBeidl, pavlinajane, webtreats, QuotesEverlasting, hannaneh710, philozopher, ArturoYee, JulienDft_Photo, DonkeyHotey, symphony of love, One Way Stock
  • Home
    • About
  • Blog
  • Tips
  • Foreman
  • Concrete Finishers
  • Layout Crew
  • online training
  • Contact
  • Share
    • Constructorator Spotlight
    • Women In Construction
    • Why I love Construction Videos
    • Technology Link Page
  • Search